Organisations are predicted to spend an increasing share of their marketing budgets on search engine optimisation in 2009. But what are the new themes and issues that will tax organisations in their efforts to make the most of search?
moreBook retailer Borders has become the latest retailer to use social media marketing. New Media Knowledge spoke to industry players about how this sector can gain from a conversational approach.
moreBeing able to compete online is a major area which small and medium-sized businesses in particular need advice. New Media Knowledge interviewed sales specialist Sean McPheat for some words of wisdom.
moreCommunications are often the weakest link in the risk management process. But a stakeholder risk information needs analysis can help, explains David Hillson... more
In order to understand a risk fully it is helpful to identify its causes as well as its effects. We can do this by using risk metalanguage to develop risk responses saysd David Hillson... more
The word "risk" is a common and widely-used part of today's vocabulary, relating to personal circumstances, society, and business. Likewise with projects. Try to establish a zero-risk project and you'd have to cancel the project before you even started it, explains David Hillson.... more
Personal risk management is among the broad range of activities to which we can apply the general principles and lessons of risk management, and New Year can be a great time to do it, explains David Hillson... more
The view that project management's tenets of processes and risk management are the antithesis of innovation needs challenging, says David Hillson... more
Some projects identify just a small number of high-level risks, while others have many hundreds or even thousands of detailed risks. Dr David Hillson explores the different levels of risk analysis by looking at management, ownership and reporting.
Risks can be identified and described at different levels of detail, and there can be considerable variation between different projects or organisations. Some projects identify just a small number of high-level risks, while others have many hundreds or even thousands of detailed risks. A generalised or high-level description of risk can make it difficult to develop responses and assign ownership, while describing risks in a lot of detail can create a great deal of work. How can we determine the correct level of detail? There are three components to consider : management, ownership, and reporting.
1. Firstly, risks should be described at the level to which they are going to be managed. A high-level description such as “Something unexpected might happen during the project” is quite useless as no management action is possible at this level. Too much detail is also pointless, for example “George Smith the junior system architect may break his right leg at the football match next Tuesday night and not be able to finish the Phase 2.4.2 detailed design drawings.” The risk might be better stated as “Key staff may not be available when required to complete the system design.” At this level the risk can be managed proactively, with careful resource planning, use of shadowing or deputies, and ensuring that key tasks are not assigned to one person. Of course it is true that some risks will need to be managed at a detailed level while others can be addressed at a higher level.
2. Secondly, each risk should be described at a level of detail where it can be assigned to a single owner, with clear responsibility and accountability for addressing the risk. However this also allows for some variation in the level of risk description, as risk owners can range from junior team members who might be responsible for detailed risks, through to the project sponsor or senior managers who are only interested in the higher level.
3. Thirdly, the level of risk description should match the reporting needs of the person receiving the risk report. Project team members need detailed risk descriptions for those risks which they are responsible for managing. The project sponsor or client needs less detail, perhaps with groups of risks being summarised into high-level descriptions.
Each of these three answers suggests that risk descriptions can be useful at various levels for different purposes. There is no one right level that meets all needs. So what can be done?
One useful tool addressing this issue is the Risk Breakdown Structure (RBS), which is a hierarchical structure describing sources of risk to the project. This allows risks to be described at increasing levels of detail throughout the project. At the top level (Level 0), all risks are simply “Project Risks”. But this can be broken down into major sources of risk at Level 1, such as Technical Risk, Commercial Risk, Management Risk, External Risk. Each of these major areas can be further detailed at Level 2 (for example Technical Risk could be subdivided into Technology, Performance, Reliability, Interfaces etc). At the lowest level individual risks are described under each specific source.
Different RBS levels can then be used for different purposes. Detailed risk reporting, ownership and management can take place at the lowest level. Higher RBS levels allow groups of risks to be rolled-up and summarised for reporting, ownership and management further up the organisation. So the project safety engineer may need to know about a specific risk affecting a particular product trial (RBS Level 4), whereas the company's Chief Technical Officer may be interested in the overall level of technical risk on the project (RBS Level 1).
Risk descriptions at different levels of detail are useful in different ways. Instead of insisting that all risks are described at a single level which may not suit all needs, using a hierarchical RBS can provide the necessary flexibility with both high-level and more detail as appropriate.
About the author: Dr David Hillson PMP FAPM
FIRM MCMI is an international risk management consultant, and
Director of Risk Doctor & Partners (www.risk-doctor.com). He is a popular
conference speaker and award-winning author on risk. He is
recognised internationally as a leading thinker and practitioner
in the risk field, and has made several innovative contributions
to improving risk management. His recent emphasis has been the
inclusion of proactive opportunity management within the risk
process, which is the topic of his latest book